William Golangco Construction Corporation vs. Philippine Commercial International Bank
The petition was granted and the Court of Appeals decision was annulled and set aside. Because the peeling of the granitite wash-out finish occurred after the expiration of the one-year defects liability period stipulated in the construction contract, and because the defects were neither hidden nor subject to an express reservation of rights, the contractor was absolved from liability for the repair costs. The contractual guarantee period, valid under the principle of autonomy of contracts, limits the contractor's liability to defects evident within one year from final acceptance.
Primary Holding
A contractor is relieved from liability for construction defects that appear after the lapse of the contractual defects liability period, provided the defects were not hidden and the employer did not expressly reserve its rights upon acceptance.
Background
William Golangco Construction Corporation (WGCC) and Philippine Commercial International Bank (PCIB) entered into a construction contract on October 20, 1989, for the extension of PCIB Tower II, which included the application of a granitite wash-out finish on the exterior walls. PCIB, with the concurrence of its consultant TCGI Engineers, accepted the completed work on June 1, 1992. WGCC submitted a one-year guarantee bond on July 1, 1992. In 1993, portions of the granitite wash-out finish began peeling off. WGCC made minor repairs but declined to redo the entire finish. PCIB subsequently hired another contractor to re-do the finish for P11,665,000 and demanded reimbursement from WGCC.
History
-
PCIB filed a request for arbitration with the Construction Industry Arbitration Commission (CIAC) for reimbursement of repair expenses.
-
CIAC declared WGCC liable for the construction defects.
-
WGCC filed a petition for review with the Court of Appeals.
-
Court of Appeals dismissed the petition for lack of merit; motion for reconsideration was denied.
-
WGCC filed a petition for review on certiorari with the Supreme Court.
Facts
- The Construction Contract: WGCC and PCIB executed a contract for the PCIB Tower II Extension Project on October 20, 1989. The project specifications included a granitite wash-out finish on the exterior walls.
- Acceptance and Guarantee: PCIB and its consultant, TCGI Engineers, accepted the turnover of the completed work on June 1, 1992. WGCC issued a guarantee bond on July 1, 1992, valid for one year, to cover any defects arising within that period as required by Article XI of the contract.
- The Defects: In 1993, more than a year after final acceptance, the granitite wash-out finish began peeling off and falling from the walls. PCIB requested WGCC to rectify the defects. WGCC performed minor repairs but informed PCIB it was "not in a position to do the new finishing work," though it offered to share the cost.
- The Repairs and Claim: PCIB hired Brains and Brawn Construction and Development Corporation to redo the entire finish, incurring expenses of P11,665,000. PCIB demanded reimbursement from WGCC, which refused, leading PCIB to initiate arbitration.
Arguments of the Petitioners
- Defects Liability Period: Petitioner argued that it is not liable for defects in the granitite wash-out finish that occurred after the lapse of the one-year defects liability period provided in Article XI of the construction contract.
- Burden of Proof: Petitioner maintained that PCIB had the burden of proof to establish the alleged defects, which PCIB failed to discharge.
- Standard of Evidence: Petitioner asserted that the CIAC and the Court of Appeals unjustly failed to observe the standard of substantial evidence required in arbitration cases.
Arguments of the Respondents
- Unfulfilled Obligations: Respondent countered that Article 62.2 of the contract (Unfulfilled Obligations) retains the contractor's liability even after the issuance of the Defects Liability Certificate for obligations incurred prior to its issuance.
- Hidden Defects: Respondent argued that the defects in the granitite wash-out finish were hidden or latent defects, thus falling under the exceptions to the rule that acceptance relieves the contractor of liability.
Issues
- Defects Liability Period: Whether WGCC is liable for defects in the granitite wash-out finish that occurred after the lapse of the one-year defects liability period provided in the construction contract.
- Unfulfilled Obligations: Whether the defects constituted "unfulfilled obligations" under Article 62.2 of the contract that remained unperformed at the time the Defects Liability Certificate was issued.
- Hidden Defects: Whether the defects were hidden, triggering WGCC's liability under Article 1719 of the Civil Code despite acceptance and the lapse of the guarantee period.
Ruling
- Defects Liability Period: WGCC is not liable for the defects. The one-year defects liability period stipulated in Article XI of the contract is valid and binding under the principle of autonomy of contracts. Such limitation is fair, equitable, and consistent with established usage in Philippine construction contracts; without it, contractors would be burdened with perpetual guarantees.
- Unfulfilled Obligations: The defects were not "unfulfilled obligations" under Article 62.2. The peeling of the finish occurred more than a year after final acceptance; thus, it was not an obligation that remained unperformed at the time the Defects Liability Certificate was issued. Furthermore, the third paragraph of Article XI did not operate as a blanket exception to, nor did it modify or supersede, the categorical one-year guarantee period in the first paragraph.
- Hidden Defects: The defects were not hidden. PCIB's team of experts supervised the workmanship, WGCC regularly submitted progress reports and photographs, PCIB had site access and exercised reasonable supervision, PCIB issued punch lists before final acceptance, PCIB supplied the materials, and PCIB's experts concurred in the turnover. Because the defects were not hidden and PCIB did not expressly reserve its rights upon acceptance, Article 1719 of the Civil Code does not apply. Any ambiguity in the contract must be interpreted against the party who caused the confusion—here, PCIB, whose consultant drafted the contract.
Doctrines
- Autonomy of Contracts — The contracting parties may establish such stipulations, clauses, terms, and conditions as they may deem convenient, provided they are not contrary to law, morals, good customs, public order, or public policy. Obligations arising from contracts have the force of law between the parties. The Court applied this doctrine to uphold the one-year defects liability period, noting that courts will not relieve a party from the effects of an unwise or unfavorable contract freely entered into.
- Acceptance of Work — Under Article 1719 of the Civil Code, acceptance of the work by the employer relieves the contractor of liability for any defect, unless (1) the defect is hidden and the employer is not expected to recognize it, or (2) the employer expressly reserves his rights. The Court found neither exception present, as the defects were evident during supervision and no rights were reserved.
- Contra Proferentem — A contract should not be interpreted to favor the party who caused the confusion. The contract was prepared by PCIB's consultant; thus, any ambiguity cannot be construed against WGCC.
Key Excerpts
- "The inclusion in a written contract for a piece of work, such as the one in question, of a provision defining a warranty period against defects, is not uncommon. This kind of a stipulation is of particular importance to the contractor, for as a general rule, after the lapse of the period agreed upon therein, he may no longer be held accountable for whatever defects, deficiencies or imperfections that may be discovered in the work executed by him." — Defines the legal effect of a contractual warranty period in construction contracts.
- "We cannot countenance an interpretation that undermines a contractual stipulation freely and validly agreed upon. The courts will not relieve a party from the effects of an unwise or unfavorable contract freely entered into." — Reiterates the binding nature of contractual stipulations under the autonomy of contracts.
Precedents Cited
- Philippine American General Insurance Co. v. Court of Appeals, 199 Phil. 248 (1982) — Followed. Established the principle that a stipulation defining a warranty period is of particular importance to the contractor, who is generally no longer accountable for defects after the lapse of the agreed period.
- Philippine Aluminum Wheels, Inc. v. Fasgi Enterprises, Inc., 396 Phil. 893 (2000) — Followed. Cited for the proposition that courts will not relieve a party from the effects of an unwise or unfavorable contract freely entered into.
Provisions
- Article 1306, Civil Code — Recognizes the autonomy of contracts, allowing parties to establish stipulations not contrary to law, morals, good customs, public order, or public policy. Applied to uphold the one-year defects liability period as a valid, binding limitation on the contractor's liability.
- Article 1159, Civil Code — States that obligations arising from contracts have the force of law between the parties and should be complied with in good faith. Applied to emphasize the obligatory nature of the agreed guarantee period.
- Article 1719, Civil Code — Provides that acceptance of the work relieves the contractor of liability for defects unless the defect is hidden or the employer expressly reserves his rights. Applied to absolve WGCC, as the defects were not hidden and no reservation of rights was made.
Notable Concurring Opinions
Reynato S. Puno, Angelina Sandoval-Gutierrez, Adolfo Azcuna, Cancio C. Garcia