Primary Holding
A motion for reconsideration is a mandatory prerequisite to a petition for certiorari under Rule 65, and an employer's separation program covering "regular, project employees and permanent employees who have rendered at least one year of continuous service" permits the cumulation of an employee's prior project assignments to satisfy the eligibility requirement, even if the last assignment alone was less than one year.
Background
Philippine National Construction Corporation (PNCC) is a government-owned construction corporation that deployed workers to various construction projects, including the Magat Dam, LRT, Saudi Arabia, PG-7B, and Molave projects. PNCC maintained a Retrenchment Program effective January 16, 1989, providing special separation benefits to eligible employees. Private respondent Lorenzo Mendoza was a Driver II repeatedly hired by PNCC for different project assignments over an eight-year span. The dispute arose when PNCC denied Mendoza's claim for separation benefits under the program, prompting him to file a complaint for non-payment of separation pay.
History
1989 – 1997-
Sep 5, 1989
Mendoza filed a complaint before the Labor Arbiter for non-payment of separation pay under PNCC's Retrenchment Program.
-
1 yr 2 mos later
-
Dec 3, 1990
Executive Labor Arbiter Valentin C. Guanio granted Mendoza's claim, ordering PNCC to pay P9,204.00 as separation pay plus 10% attorney's fees.
-
1 yr 9 mos later
-
Sep 30, 1992
NLRC affirmed the Labor Arbiter's decision in all respects except the award of attorney's fees, which it disallowed.
-
27 days later
-
Oct 27, 1992
The Supreme Court (Second Division) issued a restraining order enjoining respondents from enforcing the NLRC decision.
-
4 yrs 9 mos later
-
Aug 11, 1997
The Supreme Court (Third Division) dismissed the petition, affirmed the NLRC decision with modification reinstating attorney's fees and imposing 6% legal interest, and lifted the restraining order.
Facts
From July 14, 1981 until September 23, 1982, PNCC employed Lorenzo Mendoza as Driver II at its Magat Dam Project. A few days later, on September 27, 1982, he was rehired as Driver II at the LRT Project, where he worked until January 31, 1983. The following day, February 1, 1983, PNCC deployed Mendoza to its Saudi Arabia Project, also as Driver II, where he remained until August 1, 1984. It took more than six months for Mendoza to be repatriated to the Philippines. Upon his return, he resumed work as Driver II in PNCC's PG-7B Project from February 22, 1985 until May 18, 1986.
For more than two years afterwards, Mendoza was not given any work assignment. On August 17, 1988, he was hired anew as Driver II for PNCC's Molave Project. This last engagement lasted until June 15, 1989 — a duration of nine months and twenty-eight days. Mendoza's employment contracts explicitly described his status as "regular," and his appointment papers dated September 23, 1982 and October 6, 1982 both stated he was "a regular employee." PNCC itself characterized him as a "project employee," defining a regular employee as one who was permanent with respect to a particular project and in no instance beyond the completion of the project to which he was employed.
Thereafter, Mendoza claimed the benefits of PNCC's Retrenchment Program, which under paragraph 2.1 provided special separation benefits to "all regular, project employees and permanent employees who have rendered at least one (1) year of continuous service with PNCC and are actively employed in the company as of the date of their separation." PNCC denied his claim, contending that Mendoza was a project employee whose last assignment lasted only ten months and thus did not meet the one-year continuous service requirement. Mendoza filed a complaint for non-payment of separation pay on September 5, 1989. The executive labor arbiter granted Mendoza's claim, ordering PNCC to pay P9,204.00 as separation pay plus 10% attorney's fees. The NLRC affirmed the grant but disallowed the attorney's fees. PNCC filed a petition for certiorari with the Supreme Court without first filing a motion for reconsideration of the NLRC decision, asserting that the questions raised before the Court were the same ones considered by the NLRC.
Arguments of the Petitioners
- Evidentiary Insufficiency: Petitioner argued that the questioned decision of the labor arbiter, as affirmed by the NLRC, was not supported by evidence, applicable law, and jurisprudence.
- Employment Status and Continuity: Petitioner maintained that private respondent was a project employee and that his service with PNCC was not continuous, rendering him ineligible for separation benefits under the program.
- Prescription: Petitioner contended that the complaint was barred by Article 291 of the Labor Code, having been filed on September 5, 1989 — more than three years after Mendoza's separation from employment on May 18, 1986.
- Insufficient Last Assignment: Petitioner argued that Mendoza was employed for only ten months from August 17, 1988 to June 15, 1989, and thus did not meet the program's requirement of at least one year of continuous service at the time of separation.
Arguments of the Respondents
- Timeliness of Claim: Private respondent alleged that he could not be expected to file a claim for separation benefits within three years after 1986 because he was rehired within two years, in 1988.
- Coverage Under the Program: Private respondent contended that since he was terminated on June 15, 1989 — five months after the program's cut-off date of January 16, 1989 — he was covered by the separation program.
- Work Pool Status (Solicitor General): The Solicitor General argued that Mendoza was drawn from a "work pool" from which PNCC drew workers for assignment to projects at its discretion, implying regular employment status.
Issues
- Motion for Reconsideration: Whether a motion for reconsideration is required prior to filing a petition for certiorari.
- Entitlement to Separation Benefits: Whether private respondent Mendoza is entitled to the separation benefits under PNCC's Retrenchment Program.
Ruling
- Motion for Reconsideration: Yes. A motion for reconsideration is a mandatory requirement before resorting to certiorari, and PNCC's failure to file one constitutes a fatal infirmity warranting dismissal.
- Entitlement to Separation Benefits: Yes. Mendoza satisfied all four requisites of the program — he was a covered employee, rendered at least one year of continuous service (through cumulation of prior assignments), was actively employed as of his separation date, and was separated on or after January 16, 1989.
Ruling Rationale
-
Motion for Reconsideration: The filing of a motion for reconsideration is intended to afford the NLRC an opportunity to correct any error attributed to it through a re-examination of the legal and factual aspects of the case. Under the NLRC's New Rules of Procedure, a motion for reconsideration must be filed within ten calendar days from receipt of the decision; otherwise, the decision becomes final and executory. PNCC's bare allegation that the same questions raised before the NLRC would be raised before the Court afforded no excuse. None of the recognized exceptions to the rule applied. This procedural defect alone warranted dismissal.
-
Entitlement to Separation Benefits: The program's requisites were: (1) the employee must be either a regular, project, or permanent employee; (2) he must have rendered at least one year of continuous service; (3) he must have been actively employed as of the date of separation; and (4) he must have been separated on or after January 16, 1989. As to the first requisite, Mendoza's employment contracts explicitly described him as "regular," and even PNCC acknowledged him as a "project employee" — both categories were covered by the program. As to the second requisite, the phrase "every year of completed/credited service" in the computation of benefits did not require continuous service; the continuous service requirement pertained only to eligibility, not computation. Nothing in the program prohibited the cumulation of services rendered across different assignments. Mendoza had worked for PNCC for at least five years, one month, and seven days across five engagements. His prior stints could properly be considered to qualify him, even though his last assignment alone was less than one year. The program's plain language did not require that the continuous service be immediately prior to separation. As to the third and fourth requisites, Mendoza was actively employed until June 15, 1989, which was after the program's effectivity date. All doubts in the interpretation of an employer's separation program were construed in favor of labor, consistent with the constitutional mandate favoring the working class. The Court also reinstated the award of attorney's fees, finding that Mendoza was compelled to litigate for eight years to recover the paltry sum of P9,204.00, and that such an award was legally and morally justifiable in actions for recovery of wages.
Doctrines
-
Motion for Reconsideration as Prerequisite to Certiorari — A motion for reconsideration is a mandatory requirement before one may resort to the special civil action of certiorari. The motion affords the lower tribunal the opportunity to correct its own errors before resort to the courts. Failure to file a motion for reconsideration within the prescribed period renders the lower court's decision final and executory and constitutes a fatal procedural defect warranting dismissal of the certiorari petition. Recognized exceptions exist, but the party invoking them must demonstrate that the case falls within them; a bare allegation that the same issues will be raised does not suffice.
-
Construction of Employer Separation Programs in Favor of Labor — In the interpretation of an employer's program providing for separation benefits, all doubts should be construed in favor of labor. Workers are the intended beneficiaries of such programs, and the Constitution mandates a clear bias in favor of the working class. When conflicting interests of labor and capital are weighed on the scales of social justice, the heavier influence of capital must be counterbalanced by the sympathy and compassion the law accords the underprivileged worker.
-
Cumulation of Services Under Separation Programs — Where a separation program bases eligibility on "at least one year of continuous service" and computation on "every year of completed/credited service," the continuous service requirement pertains only to eligibility, not to the computation of benefits. Nothing in such language prohibits the cumulation of services rendered by qualified employees across different assignments. Prior stints may be considered to qualify an employee even if the last assignment alone was less than one year, provided the plain language does not require that the continuous service be immediately prior to separation.
-
Attorney's Fees in Wage Recovery Actions — In actions for recovery of wages or where an employee was forced to litigate and incur expenses to protect his rights and interests, the award of attorney's fees is legally and morally justifiable.
Key Excerpts
-
"The law is clear that a motion for reconsideration is a mandatory requirement before one may resort to the special civil action of certiorari. While there are recognized exceptions to this rule, petitioner has not convinced us that this case is one of them." — This passage states the ratio decidendi on the procedural issue, affirming the mandatory nature of the motion for reconsideration prerequisite and placing the burden on the petitioner to demonstrate that an exception applies.
-
"In the interpretation of an employer's program providing for separation benefits, all doubts should be construed in favor of labor. After all, workers are the intended beneficiaries of such program and our Constitution mandates a clear bias in favor of the working class." — This is the canonical formulation of the doctrine of construing employer separation programs in favor of labor, frequently cited in subsequent jurisprudence on labor-standard interpretation.
-
"Nothing in the phrase 'every year of completed/credited service' can be understood as requiring that the service be continuous. Thus, it should be stressed that the requirement of continuous service pertains only to one's eligibility under the program. It does not restrict the computation of separation benefits." — This passage articulates the distinction between the eligibility requirement and the computation of benefits under a separation program, establishing that prior services may be cumulated for qualification purposes.
Precedents Cited
- Interorient Maritime Enterprises vs. National Labor Relations Commission, G.R. No. 115497, September 16, 1996 — Followed. Cited for the rule that certiorari will lie only if there is no appeal or plain, speedy, and adequate remedy in the ordinary course of law, and that a motion for reconsideration is the proper remedy before resorting to certiorari.
- Labudabon vs. National Labor Relations Commission, 251 SCRA 129, December 11, 1995 — Followed. Cited for the rule that where no motion for reconsideration is filed within ten calendar days from receipt, the NLRC decision becomes final and executory.
- Zapata vs. NLRC, 175 SCRA 56, July 5, 1989 — Followed. Cited for the proposition that a motion for reconsideration is a precondition for pursuing any further remedy, and failure to file renders the NLRC decision final.
- Raycor Aircontrol Systems, Inc. vs. National Labor Relations Commission, G.R. No. 114290, September 9, 1996 — Discussed. Cited to clarify that an employee in a "work pool" is not necessarily a regular employee; he may also be a project employee, and that the existence of a work pool must be established by factual findings.
- City Fair Corporation vs. NLRC, 243 SCRA 572, April 21, 1995 — Followed. Cited for the principle that when conflicting interests of labor and capital are weighed, the heavier influence of capital must be counterbalanced by sympathy for the underprivileged worker.
- Rasonable vs. National Labor Relations Commission, 253 SCRA 815, February 20, 1996 — Followed. Cited for the rule that attorney's fees are proper in actions for recovery of wages where the employee was forced to litigate.
Provisions
- Article 291, Labor Code — Governs money claims arising from employer-employee relations, requiring filing within three years from accrual of the cause of action. Petitioner invoked this provision to argue prescription, but the Court did not rule on this point as it resolved the case on other grounds.
- Section 14, Rule VII, New Rules of Procedure of the NLRC — Requires a motion for reconsideration to be filed within ten calendar days from receipt of the NLRC decision; otherwise, the decision becomes final and executory. Applied to find PNCC's failure to file a motion for reconsideration a fatal procedural defect.
- Article 2208(2) and (7), Civil Code — Authorizes the award of attorney's fees in actions for recovery of wages and where the plaintiff was compelled to litigate to protect his rights. Applied to reinstate the labor arbiter's award of attorney's fees.
- Paragraph 2.1, PNCC Separation Program with Special Benefits — Provides coverage for regular, project, and permanent employees who have rendered at least one year of continuous service and are actively employed as of the date of separation. Construed in favor of labor to permit cumulation of prior assignments for eligibility.
- Paragraph 2.2.4, PNCC Separation Program with Special Benefits — Requires that the employee be separated on or after the effectivity date of January 16, 1989. Applied to confirm Mendoza's coverage, as he was separated on June 15, 1989.
Notable Concurring Opinions
Narvasa, C.J., Davide Jr., Melo, and Francisco, JJ., concurred. No separate concurring opinions were written.