Primary Holding
Rescission of a reciprocal contract under Article 1191 of the Civil Code does not extinguish contractually stipulated liquidated damages, as the same provision expressly allows the injured party to seek rescission "with the payment of damages in either case"; the parties' own stipulation on the consequences of breach must be maintained unless equitably reduced under Articles 1229 and 2227 on grounds of iniquity or unconscionability, not merely on the basis of a belated and inconsequential offer of rectification.
Background
The Philippine Economic Zone Authority (PEZA), a government agency tasked with administering economic zones, required additional fire trucks to address the needs of its locator-enterprises and the onset of the El Niño phenomenon. It conducted a public bidding for the acquisition of two brand-new fire trucks, which Pilhino Sales Corporation won. The contract between them was one of sale with reciprocal obligations, stipulating a penalty clause for delay in delivery. The dispute arose from Pilhino's failure to deliver the trucks, prompting PEZA to seek judicial rescission and damages.
History
-
RTC of Pasay City, Branch 108, Nov. 2, 2005 — ruled in favor of PEZA, ordering Pilhino to pay liquidated damages at 1/10 of 1% of the total contract price per day of delay from June 19, 1998, ₱100,000 in exemplary damages, declaring the contract rescinded, forfeiting the performance bond, and awarding costs.
-
Court of Appeals, May 2, 2008 — partly granted Pilhino's appeal, reducing liquidated damages to ₱1,400,000.00 and deleting the forfeiture of the performance bond, reasoning that Pilhino attempted mitigation by offering modified specifications and that PEZA had not paid any amount.
-
Court of Appeals, Nov. 25, 2008 — denied PEZA's Motion for Reconsideration.
-
Supreme Court, Second Division, Sept. 28, 2016 — granted the Petition, reversed and set aside the Court of Appeals' Decision and Resolution, and reinstated the RTC Decision.
Facts
On October 4, 1997, the Philippine Economic Zone Authority published an invitation to bid in the Business Daily for the acquisition of two brand-new fire truck units with a capacity of 4,000–5,000 liters of water and 500–1,000 liters of chemical foam, with complete accessories. Three companies participated in the bidding: Starbilt Enterprise, Inc., Shurway Industries, Inc., and Pilhino Sales Corporation. Pilhino secured the contract at an initial price of ₱3,000,000.00 per truck, later reduced to ₱2,900,000.00 per truck after negotiation, for a total contract price of ₱5,800,000.00.
The contract required Pilhino to deliver two FF3HP brand fire trucks within 45 days of receipt of a purchase order from PEZA. It further stipulated that in case of failure to deliver on the specified date, the supplier agreed to pay a penalty at the rate of 1/10 of 1% of the total contract price for each day of delay commencing on the first day after the stipulated date. PEZA furnished Pilhino with a purchase order dated November 6, 1997. Pilhino failed to deliver the trucks as committed.
PEZA made formal demands on Pilhino on July 27, 1998 and February 23, 1999. When Pilhino still failed to comply, PEZA filed a Complaint for rescission of contract and damages before the Regional Trial Court of Pasay City, docketed as Civil Case No. 00-0343 and raffled to Branch 108. In its defense, Pilhino claimed there was no starting date from which its obligation to deliver could be reckoned, suggesting that there was no meeting of minds between the parties. The Court of Appeals, however, found that Pilhino had manifested acquiescence to the purchase order by submitting a Performance Bond dated June 2, 1999 and an Indemnity Agreement dated June 9, 1998, both signed by its Vice President.
In a letter dated March 29, 1999, signed by its Hino Division Manager Edgar R. Santiago and noted by VP-Operations Roberto R. Garcia, Pilhino admitted it could no longer meet the specifications for the two fire trucks. It proposed a modified arrangement with new specifications at ₱3,600,000.00 per unit, offering to shoulder the difference between the original price of ₱2,900,000.00 per unit and the new price in lieu of the penalty, and requesting that the accumulation of the penalty be stopped. By the time this offer was made, the Complaint for rescission and damages had already been filed before the trial court.
Arguments of the Petitioners
- Entitlement to Liquidated Damages: Petitioner asserted that it already suffered damage when respondent failed to deliver the trucks on time, and that the contractually stipulated penalty of 1/10 of 1% of the contract price for every day of delay was neither unreasonable nor contrary to law, morals, or public order.
- Voluntariness of Stipulation: Petitioner maintained that the stipulation on liquidated damages was freely entered into by the parties.
- No Basis for Reduction: Petitioner argued that the Court of Appeals' computation of reduced liquidated damages had no basis in fact and law.
- Inconsequential Mitigation: Petitioner noted that by the time respondent made its offer of modified specifications, the Complaint had already been filed, rendering the offer inconsequential and hardly a remedy.
Arguments of the Respondents
- Nullification of Liquidated Damages upon Rescission: Respondent raised the question of whether a contract can be rescinded and declared void ab initio, and whether, once rescinded, a stipulation for liquidated damages contained in that same contract can be given separate force and effect distinct from the rescinded contract itself.
- Obliteration of Liability: Respondent suggested that with the rescission of its contract with petitioner must have come the negation of the contractual stipulation on liquidated damages and the obliteration of its liability for such liquidated damages.
Issues
- Survival of Liquidated Damages after Rescission: Whether contractually stipulated liquidated damages may still be awarded notwithstanding the rescission of the same contract stipulating them.
- Propriety of Reduction of Liquidated Damages: Whether the Court of Appeals properly reduced the liquidated damages due to petitioner based on respondent's supposed attempt at mitigation.
Ruling
- Survival of Liquidated Damages after Rescission: Yes. Rescission under Article 1191 of the Civil Code expressly provides for "the payment of damages in either case," and contractually stipulated liquidated damages survive rescission because the parties' own stipulation on the consequences of breach must be maintained.
- Propriety of Reduction of Liquidated Damages: No. The Court of Appeals erred in reducing the liquidated damages because respondent's offer of modified specifications was a belated reaction made after the Complaint had already been filed, was inconsequential as a remedy, and could not be accommodated under public bidding rules requiring equal footing among bidders.
Ruling Rationale
-
Survival of Liquidated Damages after Rescission: A contract of sale entails reciprocal obligations, and rescission on account of breach is provided for in Article 1191 of the Civil Code. While rescission results in mutual restitution — restoring the parties to their original situation prior to the inception of the contract — Article 1191 itself expressly states that the injured party may choose between fulfillment and rescission "with the payment of damages in either case." The very breach or delay that triggers rescission is what makes damages due. When the parties, by their own free acts of will, agreed on what those damages ought to be, they established the law between themselves. Courts confronted with the need to award damages in tandem with rescission must not lose sight of how the parties explicitly stated these consequences. To sustain respondent's position would turn delinquency into a profitable enterprise, enabling contractual breach to be the means for evading its own fallout. The Court relied on Laperal vs. Solid Homes, Inc., which held that there is no reason the parties cannot stipulate on the matter of damages in case of rescission under the Civil Code provisions governing liquidated damages. The distinction between judicial and extrajudicial rescission is immaterial for purposes of the availability of liquidated damages.
-
Propriety of Reduction of Liquidated Damages: The Court of Appeals reduced the liquidated damages to ₱1,400,000.00 based on respondent's supposed attempt at rectification by offering new specifications and shouldering the price difference. However, this offer was inconsequential: by the time it was made, the Complaint had already been filed, and PEZA was no longer capable of accommodating contractual modifications. Moreover, the contract was awarded through public bidding, and an essential element of a publicly bidded contract is that all bidders must be on equal footing. Allowing the winning bidder to later modify provisions would destroy the essence of fair competition. PEZA had already suffered damage from the mere delay, as its internal memorandum emphasized the urgency of obtaining fire trucks given the increase in locator-enterprises and the onset of El Niño. Liquidated damages are penalties meant to impress upon defaulting obligors the graver consequences of their culpability; they must make non-compliance more cumbersome than compliance. The Court of Appeals erred in frustrating the express terms of the contract that respondent actively endeavored to be awarded.
Doctrines
-
Liquidated Damages Survive Rescission under Article 1191 — Rescission of a reciprocal contract under Article 1191 of the Civil Code does not extinguish contractually stipulated liquidated damages. Article 1191 expressly provides that the injured party may choose between fulfillment and rescission "with the payment of damages in either case." The parties' own stipulation on the consequences of breach must be maintained, subject only to equitable reduction under Articles 1229 and 2227 on grounds of iniquity or unconscionability. Applied in this case to uphold PEZA's claim for liquidated damages notwithstanding the rescission of the contract for non-delivery of fire trucks.
-
Equitable Reduction of Liquidated Damages — Under Articles 1229 and 2227 of the Civil Code, liquidated damages may be equitably reduced if they are iniquitous or unconscionable, or when the principal obligation has been partly or irregularly complied with. A belated offer of modified specifications made after litigation has commenced does not constitute a valid ground for equitable reduction, especially where the contract was awarded through public bidding and modifications would violate the requirement of equal footing among bidders.
-
Nature of Liquidated Damages as Penalty — Liquidated damages are those agreed upon by the parties to be paid in case of breach. Under Philippine law, they take the nature of penalties. A penal clause is an accessory undertaking to assume greater liability in case of breach, attached to an obligation to ensure performance. Liquidated damages must make non-compliance more cumbersome than compliance.
Key Excerpts
-
"When the contracting parties, by their own free acts of will, agreed on what these damages ought to be, they established the law between themselves. Their contemplation of the consequences proper in the event of a breach has been articulated." — This passage articulates the ratio decidendi for why liquidated damages survive rescission: the parties' voluntary stipulation on the consequences of breach constitutes the law between them and must be upheld by courts.
-
"To uphold both Article 1191 of the Civil Code and the parties' will, contractually stipulated liquidated damages must, as a rule, be maintained." — This states the controlling rule that liquidated damages stipulated in a contract survive its rescission, subject only to equitable reduction under Articles 1229 and 2227.
-
"Respondent's position suggests that with rescission must necessarily come the obliteration of the punitive consequence which, to begin with, was the product of its own (along with the other contracting party's) volition. Its position turns delinquency into a profitable enterprise, enabling contractual breach to itself be the means for evading its own fallout." — This passage explains the policy rationale against allowing rescission to extinguish liquidated damages, emphasizing that such a rule would reward rather than penalize breach.
Precedents Cited
- Spouses Velarde vs. Court of Appeals, 413 Phil. 360 (2001) — Cited to explain the nature of a contract of sale as involving reciprocal obligations and the requirement of mutual restitution upon rescission under Article 1191.
- Laperal vs. Solid Homes, Inc., 499 Phil. 367 (2005) — Controlling precedent followed. Held that there is no reason the parties cannot stipulate on the matter of damages in case of rescission under the Civil Code provisions governing liquidated damages, and that mutual restitution under Article 1191 does not negate liability for liquidated damages freely stipulated upon by the parties.
- Palay, Inc. vs. Clave — Cited for the proposition that Article 1385 of the Civil Code on restitution applies to rescission under Article 1191.
- Agan, Jr. vs. Philippine International Air Terminals Co., Inc., 450 Phil. 744 (2006) — Cited for the principle that all bidders in a public bidding must be on equal footing, and that the winning bidder cannot later modify provisions of the awarded contract, as this would destroy fair competition.
- H.L. Carlos Construction, Inc. vs. Marina Properties Corp., 466 Phil. 182 (2004) — Cited for the definition and nature of liquidated damages as penalties meant to ensure performance.
Provisions
- Article 1191, Civil Code — Governs rescission of reciprocal obligations. Provides that the injured party may choose between fulfillment and rescission "with the payment of damages in either case." Applied to hold that liquidated damages survive rescission, as the provision expressly allows damages in either case.
- Article 1229, Civil Code — Authorizes the judge to equitably reduce the penalty when the principal obligation has been partly or irregularly complied with, or when the penalty is iniquitous or unconscionable. Cited by the Court of Appeals as basis for reducing liquidated damages, but the Supreme Court found the reduction improper.
- Article 2227, Civil Code — Provides that liquidated damages, whether intended as indemnity or penalty, shall be equitably reduced if iniquitous or unconscionable. Same treatment as Article 1229.
- Article 2226, Civil Code — Defines liquidated damages as those agreed upon by the parties to a contract to be paid in case of breach. Cited in the context of respondent's argument.
- Article 1385, Civil Code — Provides that rescission creates the obligation to return the things which were the object of the contract, together with their fruits, and the price with its interest. Applied to confirm that mutual restitution is required in rescission under Article 1191.
Notable Concurring Opinions
Brion (Acting Chairperson), Del Castillo, and Mendoza, JJ., concurred. Carpio, J., was on official leave.