Primary Holding
An employee hired for a specific construction project whose completion or termination is determinable at the time of engagement remains a project employee notwithstanding rehiring across multiple projects over several years, provided the employment contracts specify the project and phase of work and the employer regularly reports terminations to the DOLE; however, a project employee's dismissal prior to project completion, without proof of such completion, is illegal and entitles the employee to reinstatement with full back wages — or, if the project is completed during the pendency of the suit, back wages computed only until the date of actual project completion.
Background
Petitioner Filipinas Pre-Fabricated Building Systems (Filsystems), Inc. is a corporation engaged in the construction business, with its plant located at No. 69 Industria Road, Bagumbayan, Quezon City. Respondent Roger D. Puente was hired by Filsystems on June 12, 1989, initially as an installer and later promoted to mobile crane operator. The dispute centers on whether Puente's decade-long engagement with Filsystems constituted regular or project employment under Article 280 of the Labor Code and Department Order No. 19, Series of 1993, which governs the classification of employees in the construction industry.
History
-
Labor Arbiter Veneranda C. Guerrero dismissed the complaint for illegal dismissal for lack of merit, ordering only payment of pro-rata 13th month pay for 1999 plus 10% attorney's fees.
-
NLRC dismissed respondent's appeal and subsequent motion for reconsideration, affirming the Labor Arbiter's dismissal.
-
Court of Appeals, in CA-GR SP No. 66756, granted the petition for certiorari, annulling the NLRC decision and ordering immediate reinstatement with full back wages plus 10% attorney's fees, finding respondent to be a regular employee.
-
Supreme Court, G.R. No. 153832, March 18, 2005 — partly granted the petition, declaring respondent a project employee but finding the dismissal illegal for lack of proof of project completion, modifying the award of back wages to terminate upon actual project completion if reinstatement was no longer possible.
Facts
Respondent Roger D. Puente began working for petitioner Filipinas Pre-Fabricated Building Systems (Filsystems), Inc., a construction company, on June 12, 1989. He was initially hired as an installer and was later promoted to mobile crane operator. According to respondent, he was stationed at the company premises at No. 69 Industria Road, Bagumbayan, Quezon City, and his work was not dependent on the completion or termination of any particular project. He claimed continuous and uninterrupted employment for ten years and asserted that on October 1, 1999, he was dismissed on the ground that he was a project employee. He filed a complaint for illegal dismissal on November 18, 1999.
Petitioners countered that respondent was hired as a project employee assigned to the company's various construction projects. They presented employment contracts showing specific project assignments, each contract expressly providing that employment was good only for the duration of the project and was on a project-to-project basis, with no separation pay upon termination. Petitioners likewise maintained that after each project assignment was completed, respondent's employment was correspondingly terminated and reported to the Department of Labor and Employment. The last employment contract, accepted by respondent on August 26, 1996, designated his position as Mobile Crane Operator for the World Finance Plaza project located at Meralco Ave., Ortigas Center, Pasig City, with the assignment of "Lifting & Hauling of Materials."
The Labor Arbiter dismissed the illegal dismissal complaint for lack of merit, ordering only the payment of pro-rata 13th month pay plus attorney's fees. The NLRC affirmed this dismissal on appeal and denied the subsequent motion for reconsideration. The Court of Appeals, however, reversed, finding that the employment contracts did not specify the duration for each project as required by Article 280 of the Labor Code and that respondent had always been assigned at the company plant rather than project sites, performing tasks vital and desirable to the employer's usual business for ten continuous years. The CA concluded respondent was a regular employee and ordered reinstatement with full back wages plus 10% attorney's fees. Petitioners elevated the case to the Supreme Court via a Petition for Review under Rule 45.
Arguments of the Petitioners
- Employment Status: Petitioners argued that the Court of Appeals erred in finding respondent to be a regular employee, maintaining that his employment contracts for specific construction projects, coupled with regular DOLE termination reports, established his status as a project employee.
- Project Site Assignment: Petitioners contended that respondent actually performed work at project sites, specifically the World Finance Plaza project, as proven by the affidavit of co-employee Eduardo Briagas and respondent's own Travel Trip Reports, and that his complaint itself specified his place of work as "PROJECT TO PROJECT."
- Validity of Dismissal: Petitioners asserted that respondent's services were terminated due to the completion of the project and the absence of available construction project contracts where he could be redeployed, invoking an alleged retrenchment program.
- Jurisdiction and Procedural Errors: Petitioners challenged the Court of Appeals' jurisdiction and alleged grave abuse of discretion in giving due course to the petition for certiorari under Rule 65 and in annulling the NLRC decision.
- Remedy and Award: Petitioners opposed the CA's order of reinstatement with full back wages and 10% attorney's fees.
Arguments of the Respondents
- Regular Employment Status: Respondent argued that his work was not dependent on the completion or termination of any project and that he was continuously employed for ten years, performing tasks vital and desirable to the employer's usual business, thereby attaining regular employment status under Article 280 of the Labor Code.
- Plant Assignment: Respondent maintained that he had always been assigned at the company plant at No. 69 Industria Road, attending to the maintenance of all mobile cranes, rather than at project sites.
- Lack of Specified Duration: Respondent contended that his employment contracts did not specify the duration for each project, contrary to the requirements of Article 280, and therefore could not support project employment classification.
Issues
- Employment Status: Whether respondent Roger D. Puente is a project employee or a regular employee.
- Validity of Dismissal and Remedy: Whether respondent's dismissal was illegal and whether he is entitled to reinstatement with full back wages.
Ruling
- Employment Status: Yes, respondent is a project employee. His employment contracts specified particular projects and phases of work, his employment was co-terminous with each project, and petitioners regularly reported terminations to the DOLE, satisfying the indicators of project employment under Department Order No. 19, Series of 1993.
- Validity of Dismissal and Remedy: Yes, the dismissal was illegal, but the remedy is modified. Petitioners failed to prove that the World Finance Plaza project or the assigned phase was completed by October 1, 1999, the date of dismissal; reinstatement with full back wages is proper, but if the project was completed during the pendency of the suit, back wages are limited to the period from dismissal until the project's actual completion date.
Ruling Rationale
-
Employment Status: The Court resolved the conflicting factual findings of the NLRC and the CA, an exception to the general rule that CA factual findings are binding on the Supreme Court. Under Article 280 of the Labor Code, employment is regular when the employee performs activities usually necessary or desirable in the employer's business, except where employment is fixed for a specific project or undertaking whose completion or termination is determined at the time of engagement. Department Order No. 19, Series of 1993, which governs the construction industry, provides indicators of project employment, including that the duration and specific work are defined in the employment agreement and made clear at the time of hiring, and that terminations are reported to the DOLE. Respondent's employment contracts expressly stated that employment was "good only for the duration of the project" and was "on a Project to Project Basis," specifying the project name (World Finance Plaza), location, and assigned phase of work (Lifting & Hauling of Materials). Although the contracts did not state particular calendar dates, Clause 3.3(a) of Department Order No. 19 provides that a "day certain" — one which must necessarily come though it may not be known exactly when — suffices; the completion of the specified phase of work constituted such a day certain. Petitioners' regular submission of termination reports to the DOLE further confirmed project employment status. The Court rejected the CA's finding that respondent worked at the company plant rather than project sites, crediting the affidavit of co-employee Eduardo Briagas, respondent's Travel Trip Reports, and the complaint's own designation of his workplace as "PROJECT TO PROJECT." The Court also held that rehiring a project employee on a project-to-project basis over ten years did not ipso facto convert him into a regular employee, because Article 280 expressly excepts project employment from the regular employment rule; the practice was dictated by the practical preference for experienced construction workers.
-
Validity of Dismissal and Remedy: In termination cases, the burden of proving lawful dismissal rests on the employer. Petitioners claimed respondent's services were terminated due to project completion, but presented no allegation or proof that the World Finance Plaza project — or the phase of work to which respondent was assigned — had been completed by October 1, 1999. The inescapable presumption was that his services were terminated without valid cause prior to the expiration of his employment period, rendering the dismissal illegal. Reinstatement with full back wages, inclusive of allowances and other benefits or their monetary equivalents, computed from the date of dismissal until reinstatement, was thus warranted. However, because respondent was a project employee, if the World Finance Plaza project had been completed during the pendency of the suit, reinstatement would no longer be possible. In that event, respondent would be entitled only to his salaries and other employment benefits corresponding to the unexpired portion of his employment — from October 1, 1999 until the date of the project's actual completion — rather than back wages until reinstatement, since a project employee's employment necessarily ceases upon project completion.
Doctrines
-
Project Employment in the Construction Industry — Under Article 280 of the Labor Code and Department Order No. 19, Series of 1993, a project employee is one whose employment has been fixed for a specific project or undertaking the completion or termination of which has been determined at the time of engagement. Indicators of project employment include: (a) the duration of the specific undertaking is reasonably determinable; (b) such duration and specific work are defined in the employment agreement and made clear at hiring; (c) the work is in connection with the particular project; (d) the employee is free to offer services to other employers while awaiting engagement; (e) termination is reported to the DOLE Regional Office within 30 days; and (f) an undertaking to pay completion bonus. The Court applied these indicators and found respondent's contracts, which specified project name, location, and phase of work, together with regular DOLE reports, sufficient to establish project employment.
-
"Day Certain" in Project Employment Contracts — A "day certain" is understood as that which must necessarily come, although it may not be known exactly when. Where the final completion of a project or phase thereof is in fact determinable and the expected completion is made known to the employee, the project employee may not be considered regular, notwithstanding one year or more of continuous employment. The Court held that the employment contract's specification of the phase of work ("Lifting & Hauling of Materials" for the "World Finance Plaza" project) constituted a day certain, even without a calendar date.
-
Effect of Rehiring on Project Employment Status — The mere rehiring of a project employee on a project-to-project basis, even over a period of ten years, does not ipso facto confer regular employment status, because Article 280 of the Labor Code expressly excepts project employment from the regular employment rule. The practice of rehiring experienced construction workers is dictated by practical considerations and does not alter the employee's project employment status.
-
Burden of Proof in Termination of Project Employees — The burden of proving that an employee was lawfully dismissed lies with the employer. Employers who hire project employees must state and, when challenged, prove the actual basis for dismissal. Failure to prove that the project or assigned phase was completed at the time of termination gives rise to the presumption that the dismissal was without valid cause and prior to the expiration of the employment period, rendering it illegal.
-
Back Wages for Illegally Dismissed Project Employees — An illegally dismissed project employee is entitled to reinstatement with full back wages from the date of dismissal until reinstatement. However, if the project is completed during the pendency of the suit, reinstatement is no longer possible and the employee is entitled only to salaries and benefits corresponding to the unexpired portion of employment — from the date of dismissal until the project's actual completion date.
Key Excerpts
-
"Without a valid cause, the employment of project employees cannot be terminated prior to expiration. Otherwise, they shall be entitled to reinstatement with full back wages. However, if the project or work is completed during the pendency of the ensuing suit for illegal dismissal, the employees shall be entitled only to full back wages from the date of the termination of their employment until the actual completion of the project or work." — This is the opening statement of the decision and encapsulates the core doctrinal ruling: the interplay between project employment status, illegal dismissal, and the limitation of back wages upon project completion.
-
"A 'day' as used herein, is understood to be that which must necessarily come, although it may not be known exactly when. This means that where the final completion of a project or phase thereof is in fact determinable and the expected completion is made known to the employee, such project employee may not be considered regular, notwithstanding the one-year duration of employment in the project or phase thereof or the one-year duration of two or more employments in the same project or phase of the object." — This passage, quoted from Clause 3.3(a) of Department Order No. 19, defines the "day certain" concept that allows project employment contracts to validly fix termination without specifying an exact calendar date, a principle central to the Court's classification of respondent as a project employee.
-
"That he was employed with Petitioner Filsystems for ten years in various projects did not ipso facto make him a regular employee, considering that the definition of regular employment in Article 280 of the Labor Code makes a specific exception with respect to project employment. The mere rehiring of respondent on a project-to-project basis did not confer upon him regular employment status." — This passage articulates the doctrine that length of service through repeated project assignments does not convert a project employee into a regular employee, distinguishing project employment from the general regular employment rule.
-
"There is no allegation or proof, however, that the World Finance Plaza project -- or the phase of work therein to which respondent had been assigned -- was already completed by October 1, 1999, the date when he was dismissed. The inescapable presumption is that his services were terminated for no valid cause prior to the expiration of the period of his employment; hence, the termination was illegal." — This passage states the ratio decidendi for the illegality of the dismissal: the employer's failure to discharge its burden of proving project completion at the time of termination.
Precedents Cited
-
D.M. Consunji, Inc. vs. NLRC, 348 SCRA 441 (2000) — Cited as controlling authority for the proposition that the length of service of a project employee is not the controlling test of employment tenure, but rather whether the employment was fixed for a specific project whose completion or termination was determined at the time of engagement. Also relied upon for the rule that the burden of proving lawful dismissal rests on the employer and for the principle that a project employee whose project is completed during the pendency of a suit is entitled only to the unexpired portion of employment benefits.
-
Association of Trade Unions vs. Abella, 380 Phil. 6 (2000) — Cited to support the proposition that compliance with the reportorial requirement of submitting termination reports to the DOLE confirms project employee status.
-
Cioco vs. C.E. Construction, G.R. No. 156748 (2004) — Cited for the doctrine that the mere rehiring of a project employee on a project-to-project basis does not confer regular employment status, and that the practice of rehiring experienced construction workers is dictated by practical considerations.
-
Archbuild Masters and Construction, Inc. vs. NLRC, 251 SCRA 483 (1995) — Cited for the rule that employers must state and prove the actual basis for a project employee's dismissal, and for the principle that a project employee cannot be reinstated if the project is completed during the pendency of the suit.
-
Imbuido vs. NLRC, 329 SCRA 357 (2000) — Cited as authority for the award of reinstatement with full back wages, inclusive of allowances and other benefits or their monetary equivalents, in cases of illegal dismissal.
Provisions
-
Article 280, Labor Code (Regular and Casual Employment) — Defines regular employment as employment engaged to perform activities usually necessary or desirable in the employer's usual business or trade, except where employment is fixed for a specific project or undertaking whose completion or termination is determined at the time of engagement, or where work is seasonal. The Court applied this provision to distinguish project employment from regular employment, holding that the specific exception for project employment prevails over the general regular employment rule even where the employee has been rehired across multiple projects for ten years.
-
Department Order No. 19, Series of 1993 (DOLE) — Governs employment in the construction industry, classifying employees as project or non-project employees and providing indicators of project employment (Section 2.2), the "day certain" rule for determining whether project employees with at least one year of service become regular (Clause 3.3(a)), and guidelines on project completion and rehiring (Section 2.3). The Court relied on these provisions to classify respondent as a project employee and to determine the effect of project completion on his entitlement to reinstatement and back wages.
Notable Concurring Opinions
Justices Sandoval-Gutierrez, Corona, Carpio-Morales, and Garcia concurred in the decision. No separate concurring opinions were noted.